August 2022 and August 2023
This project involved the installation of an Intrusion Detection and Duress alarm system, an Access Control System using electronic locks and card readers, and an IP based Video Surveillance system including cameras, recording / storage system, and backup power.
It was followed up by a support request 1 year later.
Good afternoon Marco,
Thank you so much for the information – this is exactly what I was needing.
Your assistance is very much appreciated – you all have been so great to work with throughout the entire process and then some.
Have a great day!
Respectfuly,
Tom Frazier
District Manager, Oak Ridge, TN SSA (A51)
888-250-4349 ext 23150
March 2021 - June 2021
This project involved the remodel of an existing Social Security Administration field office. All the existing lights were rewired to take existing Direct Drive LED light tubes. The lobby lighting was moved as required and LED can lights added to service windows. The whole office was rewired for data and a new PA system was installed.
Good Afternoon Bill –
Mike and his crew came today and completed the punch list items. I think they are returning tomorrow to collect their things. I was very pleased with the job they did. And, I might add, of all the subcontractor crews we’re experienced working with during this renovation, Mike & his team were always very efficient & professional. Many of the items they had to return to “fix” were due to other’s interference/sabotaging their work after they had finished….and only a couple of the items were oversights (admittedly) by them….which I understand happens. He was very apologetic for the inconvenience of having to return and was most courteous and professional in his demeanor.
I appreciate Mike and his team and I hope I may get to work with them again, if we get approval for a new Security System.
Thanks Bill!
Christine S Graves| District Manager | DO 658
550 Commerce Dr | Lakeland, FL 33813
(: 877.561.4143 or TSRP: 6-2331-25240 | 7: 863.709.8385 | *: chris.graves@ssa.gov
June 2017 - July 2017
This project involved upgrading 419 wireless APs throughout the entire Veterans Administration Hospital campus in Dublin, GA. 41 data cables were to be replaced or run anew. All existing and new cabling to be tested to CAT 5e specification.
Anita,
The 1-for-1 AP swaps at Dublin are complete.
I’d just like to say what a fabulous job your techs did. Marco communicated clearly and provided all deliverables in a timely fashion and the swaps were completed ahead of schedule.
The cable runs and new APs are being handled by Chris Furbush, so my part is complete.
Thank you again!!
Deanna A. Jenkins
Project Facilitator
Concert Technologies
November 2014
This project involved installing a fixed rack system to replace an existing rack system in a Social Security Administration field office. Then moving all cabling and patch panels from the existing rack to the new rack at cut-over while certifying all cabling at existing cat 5e specifications.
Good morning Anita,
All went well last evening in Meridian. It was a pleasure working with both of those guys.
Thanks,
Kat
Kat Lukens
SSA
June-August 2013
This project involved the fit out of a new office for the Internal Revenue Service in Decatur, GA. Installation of over 300 drops and 2 LAN rooms with associated rack hardware. A fiber optic link between the two LAN rooms was installed and a 25 pair telephony cable over 300 ft from the Telephony closet for the building to one of the LAN rooms was run. All network cabling was installed and certified to CAT6 standard.
Hello, I want to take this time to thanks Computer Solutions for the excellent wiring solution that was done at Decatur GA. All the staff was professional, polite, customer service oriented, and perfectionist. They were always prepared and willing to complete a task. When extra cables were needed to be pulled or relocated for copiers on Tuesday afternoon which required an extra effort on their part, they did without hesitations. Again I want thank all the staff but especially Chan and Marco for their great work ethic and knowledge of the craft. I have had many wiring vendors, don’t get impressed that easily, but you guys did it.
Janet Samuel
IT Specialist (Network Services)
Dec 2012 - March 2013
After doing a Site survey for a network upgrade, we advised and then helped implement a staged upgrade of existing cabling in the Internal Revenue Service regional office in Birmingham, AL.
The upgrade involved running over 250 new data cables over 2 floors, replacing existing rack and patch panels with newer cat 6 rated systems, and certifying all network cables (new and existing) to cat 6 standards. All this was accomplished while minimally impacting the day-to-day operations of the office.
Good Morning,
I just wanted to take a moment tell you what a great job the guys on Chan's crew have done. Chan and his crew have worked very hard on the Birmingham site, and did a great job with Homewood CI as well. They are a pleasure to work with, and have a work ethic second to none. I would be happy to see them on future convergence sites that I am responsible for because I know the job will be done right.
Thanks for a job well done!
Respectfully,
Adam Gibson
Telecomm. Spec.
IRS : IT/EN